The Treasury Department has signed the receipt - handover of assets. Project to manage and operate the main water pipeline system in the eastern region (Dok Krai Water Pipeline Project) to VSK, the new management.

News

       On December 31, 2023, Mr. Sommat Maneeyan, Deputy Director-General of the Treasury Department, along with Mrs. Khemaruedee Chankong, Director of the Regional Crown Property Administration Division, Mr. Krirkchai Phromduang, Treasury Department of Chonburi. Miss Pinsiri Phianthanyakarnkul Rayong Area Treasury, Treasury Department officials, Representatives of water resources management and development companies Eastern Region Public Company Limited and company representatives VSK held a meeting to discuss the case of handing over assets for the project to manage and operate the main water pipeline system in the eastern region (Dok Krai Water Pipeline Project).

         The meeting determined guidelines for receiving and handing over the project together, which will be signed. The Ministry of Finance through the Treasury Department has arranged a lease/management agreement with Eastern Water Resources Management and Development Public Company Limited (EASTW) or East Water has a period of 30 years from January 1, 1994 to December 31, 2023. For the Dok Krai Water Pipeline Project, East Water Company must deliver the assets to Treasury Department on December 31, 2023 and the Treasury Department plans to deliver it to VSK on January 1, 2024.

          Mr. Sommat Maneeyan, Deputy Director-General of the Treasury Department Authorized person to act on behalf of the Ministry of Finance and the group inspected the property delivery area together with East Water and the new operator. There was a three-party meeting regarding the handover of assets. and examined related documents on the afternoon of December 31, 2023, with the Treasury Department confirming their delivery.Therefore, a memorandum of acceptance and delivery of assets belonging to the Ministry of Finance was signed. Project to manage and operate the main water pipeline system in the eastern region Dok Krai Water Pipeline Project and delivered to the VSK new management.

          Consisting of 
1. Dok Krai - Map Ta Phut water pipeline project, which assets consist of Dokkrai water pumping station, Water raising tank (Mab Kha), steel pipe size 1,350 millimeters, with accessories, 26.50 kilometers.
2. The Map Ta Phut - Sattahip water pipeline project consists of a water raising tank (Map Ta Phut), a raw water receiving pond, Raw water receiving pool, Map Ta Phut Pumping Station, steel pipe size 900 millimeters, with accessories 8.20 kilometers, Map Ta Phut Water Pumping Station, steel pipe size 700 millimeters, with accessories 14.30 kilometers.
3. Nong Kho - Laem Chabang Water Pipeline Project (Phase 1), Chonburi Province Consisting of a Laem Chabang water intake pond, steel pipe size 1,000 millimeters and accessories 10.60 kilometers , Steel pipe size 900 millimeters with accessories 4.40 kilometers and steel pipe size 600 millimeters with accessories 14.90 kilometers.

As for the Nong Pla Lai - Nong Kho project and the Nong Kho - Laem Chabang project (Phase 2), Eastern Water Resources Development and Management Public Company Limited handed over the assets to the Treasury Department. on April 11, 2023 and the Treasury Department delivered it to VSK on April 12, 2023.

#วงษ์สยามก่อสร้าง #VSK #VongsayamKorsang #งานวางท่อ   #บริหารจัดการระบบท่อส่งน้ำ #ผู้รับเหมาก่อสร้าง #EEC #กรมธนารักษ์